File #: 2023-049   
Type: Administrative Item Status: Passed
In control: Board of Commissioners
On agenda: 2/7/2023 Final action: 2/7/2023
Title: Agreement with Central Roofing for Ramsey County Courthouse/City of Saint Paul City Hall Roof Improvement Project
Sponsors: Property Management
Attachments: 1. Contract with Central Roofing Company, 2. Resolution

                                                                                                         

Sponsor: Property Management

 

Title

title

Agreement with Central Roofing for Ramsey County Courthouse/City of Saint Paul City Hall Roof Improvement Project

end

 

Recommendation

recommendation

1.   Approve the selection of and agreement with Central Roofing Company, 4550 Main Street NE, Minneapolis, MN 55421, for the Ramsey County Courthouse/City of Saint Paul City Hall Roof Improvement Project, for the period of February 7, 2023 through February 6, 2025, in the not-to-exceed amount of $2,699,000.                                                                         

2.   Authorize the Chair and the Chief Clerk to execute the agreement.

3.   Authorize the County Manager to execute change orders and amendments to the agreement in accordance with the county’s procurement policies and procedures, provide the amounts are within the limits of available funding.

end

 

Background and Rationale

body

The Ramsey County Courthouse/Saint Paul City Hall roof and select HVAC systems are nearing their useful lifecycles and need replacement. In October of 2018, Ramsey County Property Management procured the professional services of Encompass Inc. to perform a condition assessment of the 19th and 20th floor roofs and HVAC equipment. The assessment revealed areas of roof membrane, roof flashing, and HVAC ductwork that showed early signs of failure and potential for moisture intrusions. The assessment recommended roof replacement and HVAC ductwork in 3-5 years. On October 4, 2022, Encompass Inc, submitted final copies of the project specifications and plans to Ramsey County Property Management to be included in the procurement process. The project timeline has a tentative start date of February 7, 2023, and substantial completion date of August 15, 2023.

 

On October 19, 2022, in accordance with county procurement policies and procedures, a competitive solicitation for the project was issued. Below is the competitive solicitation summary:

 

                     Request for Bids Title: Courthouse Roof Improvement Project

                     Request for Bids Release Date: October 19, 2022

                     Request for Bids Response Due Date: November 17, 2022

                     Number of Contractors Notified: 1426

                     Number of Request for Bids Responses Received: 1

                     Contractor Recommended: Central Roofing Company

 

Central Roofing Company was the only responsive and responsible bidder for the project. It has been determined that a Project Labor Agreement will not be required for the project.

end

 

County Goals (Check those advanced by Action)

       Well-being             Prosperity                 Opportunity                 Accountability

 

Racial Equity Impact

The racial equity impact of this project is not fully known. The project will include workforce inclusion goals of 32% minority and 20% women, as well as a goal of utilizing 32% certified small businesses (SBEs) found in the CERT directory recognized by the county as the acceptable source for SBE subcontractors and suppliers in conformance with the county's approved policy on workforce inclusion and contracting goals.

 

Community Participation Level and Impact

The Capital Improvement Program Advisory Committee (CIPAC), made up of Ramsey County residents appointed by the Ramsey County Board, reviews the projects submitted for the Capital Improvement Program Fund. This solicitation was issued in accordance the county' s procurement policies and procedures.

 

  Inform              Consult                                 Involve                      Collaborate        Empower                     

 

Fiscal Impact

The project is funded by $548,700 from the 2021 Ramsey County Courthouse Capital Improvement Program (CIP) Building Improvement budget and $2,150,300 from the 2023 CIP Major Project for the Ramsey County Courthouse/City of Saint Paul City Hall Roof Improvement Project.

 

 

Last Previous Action

On February 1, 2022, the Ramsey County Board of Commissioners resolved that a Project Labor Agreement shall not be used for the Ramsey County Courthouse/Saint Paul City Hall roof improvement project (B2022-043).

 

Attachments

1. Agreement with Central Roofing Company